Work done by 8 men is completed in 10 days. The same work can be completed in 12 days when done by 10 women. How many days will it take to complete when 4 men and 4 women are employed to perform the same job?

(SSC CGL Tier-1 2023 (19 Jul · Shift 3 · 2:30 PM))
  1. 12
  2. 6
  3. 10
  4. 8
Answer (Detailed Solution Below)
Option 1 : 12

Detailed Solution

Concept approach

Work = 8 × 10 = 80 man-days = 10 × 12 = 120 woman-days

⇒ 2 M = 3 W

⇒ 4M + 4W = 6W + 4W = 10W

⇒ 120/10 = 12 days

Ultra Calci trickefficiency units

8M × 10 = 10W × 12 → 80M = 120W → M = 3, W = 2 units

work = 240; 4M + 4W = 12 + 8 = 20 per day → 240/20 = 12 days

⇒ 12