Virat can complete a work in 30 days and Daniel is 60% more efficient than Virat to complete the same work. Find the total time taken by Daniel to complete the work.

(SSC CGL Tier-1 2023 (14 Jul · Shift 3 · 2:30 PM))
  1. 16⅗ days
  2. 18¾ days
  3. 19⁵⁄₃ days
  4. 17⁵⁄₃ days
Answer (Detailed Solution Below)
Option 2 : 18¾ days

Detailed Solution

Concept approach

Eff Virat : Daniel = 100 : 160 = 5 : 8

⇒ time 8 : 5

⇒ 30 × 5/8 = 18¾ days

⇒ B