A can complete
of a work in 9 days. In
5
how many days can A complete the whole work?
(SSC Selection Post 2026 (Matric, 19 Sep, Shift 3))
- 12 days
- 14 days
- 15 days
- 18 days
Answer (Detailed Solution Below)
Option 3 : 15 days
Detailed Solution
Concept approach
3/5 work in 9 days
⇒ whole = 9 × 5/3 = 15 days