A can complete
of a work in 9 days. In
5
how many days can A complete the whole work?

(SSC Selection Post 2026 (Matric, 19 Sep, Shift 3))
  1. 12 days
  2. 14 days
  3. 15 days
  4. 18 days
Answer (Detailed Solution Below)
Option 3 : 15 days

Detailed Solution

Concept approach

3/5 work in 9 days

⇒ whole = 9 × 5/3 = 15 days