P and Q can do a job in 24 days, Q and R can do it in 30 days, while P and R can do it in 40 days. X is four times as efficient as P, Y is half as efficient as Q, and Z is 2.5 times as efficient as R. Determine the number of days required to complete the same job if X, Y and Z work together.
(SSC CGL Tier-1 2023 (20 Jul · Shift 3 · 2:30 PM))
- 9
- 12
- 8
- 10
Answer (Detailed Solution Below)
Option 4 : 10
Detailed Solution
Concept approach
LCM 120
⇒ P+Q = 5, Q+R = 4, P+R = 3
⇒ P+Q+R = 6
⇒ P = 2, Q = 3, R = 1
⇒ X = 8, Y = 1.5, Z = 2.5
⇒ 12
⇒ 120/12 = 10 days
Ultra Calci trickefficiency units
LCM 120 → P + Q = 5, Q + R = 4, P + R = 3 → all = 6 → P = 2, Q = 3, R = 1
X = 8, Y = 1.5, Z = 2.5 → 12 per day → 120/12 = 10 days
⇒ 10
P और Q एक कार्य को 24 दिन में, Q और R 30 दिन में तथा P और R 40 दिन में पूरा कर सकते हैं। X, P से चार गुना कुशल है, Y, Q से आधा कुशल है और Z, R से 2.5 गुना कुशल है। यदि X, Y और Z साथ काम करें तो उसी कार्य को पूरा करने में कितने दिन लगेंगे?
(SSC CGL Tier-1 2023 (20 Jul · Shift 3 · 2:30 PM))
- 9
- 12
- 8
- 10
उत्तर (विस्तृत हल नीचे)
विकल्प 4 : 10
विस्तृत हल
कॉन्सेप्ट से हल
LCM 120
⇒ P+Q = 5, Q+R = 4, P+R = 3
⇒ P+Q+R = 6
⇒ P = 2, Q = 3, R = 1
⇒ X = 8, Y = 1.5, Z = 2.5
⇒ 12
⇒ 120/12 = 10 दिन
अल्ट्रा कैलसी ट्रिकefficiency units
LCM 120 → P + Q = 5, Q + R = 4, P + R = 3 → तीनों = 6 → P = 2, Q = 3, R = 1
X = 8, Y = 1.5, Z = 2.5 → 12 प्रतिदिन → 120/12 = 10 दिन
⇒ 10
ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →