A can do ⅓ of a work in 30 days. B can do ⅖ of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

(SSC CGL Mains 2019 (16 Nov 2020))
  1. 15 days
  2. 10 days
  3. 18 days
  4. 12 days
Answer (Detailed Solution Below)
Option 4 : 12 days

Detailed Solution

Concept approach

A: ⅓ in 30 d

⇒ 90 d; B: ⅖ in 24 d

⇒ 60 d; LCM 180: A = 2, B = 3

20 × 5 = 100

⇒ left 80 in 8 d

⇒ C = 10; A + B + C = 15/day

⇒ 180/15 = 12 days

Ultra Calci trickLCM work

A: 1/3 in 30

⇒ 90 days; B: 2/5 in 24

⇒ 60 days

⇒ LCM 180

⇒ A = 2, B = 3 per day

20 days (A + B) = 20 × 5 = 100

⇒ left 80 done by C in 8 days

⇒ C = 10 per day

A + B + C = 15 per day

⇒ 180/15 = 12 days

⇒ 12 days ✓