A, B and C can do a work in 10, 12 and 15 days respectively. They begin the work together but after 3 days C left the work, and B left 4 days before the completion of the work. In how many days will the total work be completed?

  1. 58/11
  2. 67/11
  3. 58/13
  4. 68/11
Answer (Detailed Solution Below)
Option 4 : 68/11

Detailed Solution

Concept approach

Total = 60; A 6, B 5, C 4. 6T + 5(T − 4) + 4×3 = 60

⇒ 11T = 68

⇒ T = 68/11 days

Ultra Calci trickLCM work

LCM 60: A 6, B 5, C 4 per day; total T days

6T + 5(T − 4) + 4 × 3 = 60 → 11T = 68

⇒ 68/11 ✓