Akash and Vikash can complete a work in 40 days and 60 days, respectively. In how many days will the entire work be completed if they work on alternate days, starting with Akash?

(SSC CPO Paper-1 2024 (29 Jun 2024, Shift 1))
  1. 52
  2. 50
  3. 48
  4. 42
Answer (Detailed Solution Below)
Option 3 : 48

Detailed Solution

Concept approach

LCM(40, 60) = 120

⇒ Akash 3, Vikash 2

2 days = 5

⇒ 24 pairs = 48 days = 120

48 days