45 men working 5 hours a day are to complete 60% of a job in 12 days (and the whole job at this planned rate). If after 10 days only 40% of the work is completed, how many extra hours per day will be required to complete the job on time without increasing the number of men?

  1. 2 hours
  2. 5 hours
  3. 7 hours
  4. None of these
Answer (Detailed Solution Below)
Option 4 : None of these

Detailed Solution

Concept approach

5 × 10/40% = 10 × x/60%

⇒ x = 7.5 h (100% = 20 days)

⇒ 2.5 h extra

⇒ none of these