4 men, working together, can finish a work in 18 days. How many more men are required to finish the same work in 12 days?

(SSC CGL Tier-1 2023 (25 Jul · Shift 4 · 5:15 PM))
  1. 4
  2. 3
  3. 2
  4. 6
Answer (Detailed Solution Below)
Option 3 : 2

Detailed Solution

Concept approach

Work = 4 × 18 = 72

⇒ 12 days

⇒ 72/12 = 6 men

⇒ 6 − 4 = 2 more

⇒ option C