J can complete a work in 21 days, K can complete it in 42 days and L can complete it in 63 days. If J, K and L work together, in how many days can they complete the work?

(SSC MTS 2022 (08 Jul 2022, Shift 2))
  1. 11⁶⁄₁₁
  2. 11³⁄₁₁
  3. 11⁴⁄₁₁
  4. 11⁵⁄₁₁
Answer (Detailed Solution Below)
Option 4 : 11⁵⁄₁₁

Detailed Solution

Concept approach

Efficiency (LCM 126): 6 + 3 + 2 = 11

⇒ 126/11 = 11 5/11 days.