Three men and 4 women can do a piece of work in 7 days, whereas 2 men and 1 woman can do it in 14 days. Seven women will complete the same work in:

(SSC CGL Mains 2019)
  1. 10 days
  2. 12 days
  3. 8 days
  4. 9 days
Answer (Detailed Solution Below)
Option 1 : 10 days

Detailed Solution

Concept approach

7(3m + 4w) = 14(2m + w)

⇒ 7m = 14w

⇒ m = 2w. Work = 7 × 10w = 70w

⇒ 7 women take 10 days