Pankaj can break stones for a floor alone in 16 hours, while Tarun takes 24 hours. They work on alternate hours, Pankaj starting in the first hour. In how many hours will the work be completed?

(SSC Selection Post Phase-X)
  1. 21
  2. 19
  3. 22
  4. 23
Answer (Detailed Solution Below)
Option 2 : 19

Detailed Solution

Concept approach

Total = 48: P = 3, T = 2

⇒ 2 hours = 5

⇒ 18 hours = 45

⇒ remaining 3 by Pankaj in 1 hour

⇒ 19 hours

Ultra Calci trickLCM work

LCM 48 → Pankaj = 3, Tarun = 2 per hour

⇒ 2 hours = 5

9 pairs = 18 hours = 45; left 3 → Pankaj in hour 19 finishes it

⇒ 19 hours