A and B together can do a piece of work in 20 days. A worked for 15 days and left. B finished the remaining work alone in 42 days. In how many days could B finish the whole work alone?

(SSC CPO Paper-1 2025 (11 Dec 2025, Shift 1))
  1. 80
  2. 90
  3. 108
  4. 99
Answer (Detailed Solution Below)
Option 3 : 108

Detailed Solution

Concept approach

1/A + 1/B = 1/20

⇒ 1/A = 1/20 − 1/B

A alone 15 days, then B alone 42 days: 15/A + 42/B = 1

15/20 − 15/B + 42/B = 1

⇒ 27/B = 1/4

⇒ B = 108

Ultra Calci trickmultiple-of-27 (equation subtraction)

Reading: A worked 15 days, B worked 42 days: 15A + 42B = 1 and 15(A + B) = 15/20 = 3/4

⇒ 27B = 1/4

⇒ B = 1/(27 × 4) → multiple of 27

80 ✗ 90 ✗ 99 ✗ (none ÷27) 108 ✓ (27 × 4)

⇒ 108 days