A alone can do a piece of work in 12 days. B alone can do the same work in 18 days. C alone can do the same work in 24 days. In how many days will they complete 65% of the work, if all three work together?

(SSC MTS 2022 (08 Jul 2022, Shift 1))
  1. 3.6 days
  2. 3.9 days
  3. 4.2 days
  4. 4.5 days
Answer (Detailed Solution Below)
Option 1 : 3.6 days

Detailed Solution

Concept approach

Efficiency (LCM 72): 6 + 4 + 3 = 13 per day

⇒ 65% of 72 = 46.8

⇒ 46.8/13 = 3.6 days.