A can complete a project in 10 days. How many days will A take to complete 60% of the project?

(SSC Selection Post 2026 (Matric, 24 Sep, Shift 3))
  1. 4 days
  2. 5 days
  3. 6 days
  4. 7 days
Answer (Detailed Solution Below)
Option 3 : 6 days

Detailed Solution

Concept approach

60% of 10 days = 6 days