A takes twice as long to finish a work as B and C together take, and B takes twice as long as A and C together take. A, B and C together can finish the job in 30 days. How much time will C alone take?

(Delhi Police 2021)
  1. 90 days
  2. 50 days
  3. 63 days
  4. 72 days
Answer (Detailed Solution Below)
Option 1 : 90 days

Detailed Solution

Concept approach

A = (B + C)/2

⇒ A = 1/3 of total; B = (A + C)/2

⇒ B = 1/3 of total

⇒ C = 1/3

⇒ C alone takes 3 × 30 = 90 days