A can complete a task in 18 days and B in 32 days. They start working together but B works only for 8 days; thereafter the work is completed by A. If they received ₹8,800 on completion, what is A's share (in ₹)?

(SSC Selection Post Phase-X 04.08.2022 (Shift-2))
  1. 5500
  2. 6600
  3. 6400
  4. 7200
Answer (Detailed Solution Below)
Option 2 : 6600

Detailed Solution

Concept approach

B's work = 8/32 = 1/4

⇒ A's work = 3/4

⇒ 3/4 × 8800 = ₹6600