The ratio of competencies A, B and C is 4: 5: 3. On working together, all three of them complete work in 25 days. In how many days will both A and C together complete 35% of the work?

(SSC CGL Tier-1 2018 (4 Jun · Shift 2))
  1. 18 days
  2. 15 days
  3. 12 days
  4. 10 days
Answer (Detailed Solution Below)
Option 2 : 15 days

Detailed Solution

Concept approach

Efficiency 4 : 5 : 3 = 12 units/day; work = 12 × 25 = 300. A + C = 7 units/day.

35% of 300 = 105

⇒ 105 ÷ 7 = 15 days

⇒ 15 days