If 330 persons can complete the construction of a shopping complex in 50 days, how many persons are required to complete the same work in 30 days?

(RRB JE CBT-1 2024 (18 Dec 2024, Shift 3))
  1. 505
  2. 198
  3. 450
  4. 550
Answer (Detailed Solution Below)
Option 4 : 550

Detailed Solution

Concept approach

Men × days = constant

⇒ 330 × 50 = x × 30

x = 330 × 50/30 = 550