If Arun can complete 2/3 rd of a work in 12 days, then in how many days can he complete 1/6 th of the same work?
(SSC CPO Paper-1 2023 (05 Oct 2023, Shift 3))
- 3
- 4
- 5
- 2
Answer (Detailed Solution Below)
Option 1 : 3
Detailed Solution
Concept approach
2/3 work in 12 days
⇒ 1/6 = (1/6)/(2/3) = 1/4 of that
⇒ 12/4 = 3 days
⇒ option A.