Anand can do a work in 45 days and Bahuguna in 5 days less. They started together; Bahuguna left after some days and Anand finished the remaining work in 56 days working at half of his efficiency (he worked at full efficiency while with Bahuguna). For how many days did they work together?

  1. 6
  2. 8
  3. 7
  4. 9
Answer (Detailed Solution Below)
Option 2 : 8

Detailed Solution

Concept approach

Total = 360: Anand = 8, Bahuguna = 9. Anand alone at half efficiency: 4 × 56 = 224

⇒ together did 136 at 17 per day

⇒ 8 days