A, B and C undertake a piece of work for Rs 1350. A alone can do the work in 10 days while the efficiency ratio of A to B is 6 : 5. With the help of C, they finish the whole work in 4 days. The share of C will be:

  1. Rs 310
  2. Rs 280
  3. Rs 460
  4. Rs 360
Answer (Detailed Solution Below)
Option 4 : Rs 360

Detailed Solution

Concept approach

B = 12 days. In 4 days A = 4/10, B = 4/12

⇒ C = 1 − 2/5 − 1/3 = 4/15

⇒ 4/15 × 1350 = Rs 360