A and B can do a piece of work in 6 days and 8 days respectively. With the help of C, they completed the work in 3 days and earned Rs 1,848. What was the share of C?

(SSC CGL Mains 2018)
  1. Rs 924
  2. Rs 693
  3. Rs 462
  4. Rs 231
Answer (Detailed Solution Below)
Option 4 : Rs 231

Detailed Solution

Concept approach

3 days: A = 1/2, B = 3/8

⇒ C = 1/8

⇒ 1848/8 = Rs 231