P can work thrice as fast as Q. Working independently, Q can complete a task in 24 days. In how many days can P and Q together finish the same task?

(SSC CHSL 2020 (18 Mar 2020, Shift 2))
  1. 6
  2. 4
  3. 8
  4. 5
Answer (Detailed Solution Below)
Option 1 : 6

Detailed Solution

Concept approach

P's speed = 3 × Q

Q = 24 days

⇒ P = 8 days

Together: 1/8 + 1/24 = 4/24 = 1/6