35 men can do a piece of work in 8 days. Find the time required by 16 men to do four times the work.

(SSC CGL Tier-1 2025 (22 Sep · Shift 1 · 9:00 AM))
  1. 70 Days
  2. 65 Days
  3. 60 Days
  4. 66 Days
Answer (Detailed Solution Below)
Option 1 : 70 Days

Detailed Solution

Concept approach

Work = 35 × 8 = 280 man-days × 4 = 1120

⇒ 1120/16 = 70 days

Ultra Calci trickmultiple-of-35

Work = 35 × 8 × 4 ÷ 16 → 8 × 4 = 32, so 16 cancels fully → 35 × 2

Answer is a multiple of 35

65 ✗ 60 ✗ 66 ✗ 70 ✓

⇒ 70 days