A contractor takes up the work of making a road 2189 km long in 15 months and engages 252 men. After 1/5 of the time he finds that only 1/6 of the work has been completed. How many more men should now be employed to complete the work in time?

  1. 57
  2. 64
  3. 59
  4. 63
Answer (Detailed Solution Below)
Option 4 : 63

Detailed Solution

Concept approach

3 × 252/1 = 12 × x/5

⇒ x = 315

⇒ more men = 315 − 252 = 63