A and B are equally efficient, and each can individually complete a piece of work in 36 days, if none takes any holiday. A and B started working together on this piece of work, but A took a day off after every five days of work, while B took a day off after every seven days of work. If the duo had started work on 1 July 2021, on which date was the work completed?
(SSC CPO Paper-1 2023 (05 Oct 2023, Shift 3))
- 22 July 2021
- 19 July 2021
- 21 July 2021
- 20 July 2021
Answer (Detailed Solution Below)
Option 3 : 21 July 2021
Detailed Solution
Concept approach
Work = 36, each 1/day. A off on days 6, 12, 18…; B off on days 8, 16, 24…
by day n: A = n − ⌊n/6⌋, B = n − ⌊n/8⌋
day 20: 17 + 18 = 35; day 21: 18 + 19 = 37 ≥ 36
done on day 21
⇒ 21 July 2021
A और B समान रूप से दक्ष हैं, और यदि कोई भी छुट्टी न ले तो प्रत्येक अकेले किसी कार्य को 36 दिनों में पूरा कर सकता है। A और B ने इस कार्य पर एक साथ कार्य करना शुरू किया, लेकिन A ने प्रत्येक पाँच दिन के कार्य के बाद एक दिन की छुट्टी ली, जबकि B ने प्रत्येक सात दिन के कार्य के बाद एक दिन की छुट्टी ली। यदि दोनों ने 1 जुलाई 2021 को कार्य शुरू किया था, तो कार्य किस तारीख को पूरा हुआ?
(SSC CPO Paper-1 2023 (05 Oct 2023, Shift 3))
- 22 जुलाई 2021
- 19 जुलाई 2021
- 21 जुलाई 2021
- 20 जुलाई 2021
उत्तर (विस्तृत हल नीचे)
विकल्प 3 : 21 जुलाई 2021
विस्तृत हल
कॉन्सेप्ट से हल
काम = 36, प्रत्येक 1/दिन। A की छुट्टी दिन 6, 12, 18…; B की दिन 8, 16, 24…
n दिन में: A = n − ⌊n/6⌋, B = n − ⌊n/8⌋
दिन 20: 17 + 18 = 35; दिन 21: 18 + 19 = 37 ≥ 36
21वें दिन पूरा
⇒ 21 जुलाई 2021