25 men can complete a task in 16 days. Four days after they started working, 5 more men with equal workmanship joined them. How many days will be needed by all to complete the remaining task?

(SSC CHSL 2020)
  1. 12 days
  2. 10 days
  3. 15 days
  4. 18 days
Answer (Detailed Solution Below)
Option 2 : 10 days

Detailed Solution

Concept approach

Work = 25 × 16 = 400; 4 days = 100

⇒ left 300 ÷ 30 men = 10 days