P, Q and R, when working individually, can complete a job in, respectively, 36 days, 48 days and 144 days. P, Q and R start working together. P leaves the job 12 days before completion and Q leaves the job 8 days before completion. R works from the beginning till the end of the job. Determine the total number of days taken to complete the job.
(SSC CPO Paper-1 2023 (03 Oct 2023, Shift 1))
- 24
- 27
- 30
- 25
Answer (Detailed Solution Below)
Option 2 : 27
Detailed Solution
Concept approach
LCM(36, 48, 144) = 144
⇒ P = 4, Q = 3, R = 1
Total T days: R = T, Q = T − 8, P = T − 12
4(T − 12) + 3(T − 8) + T = 144
⇒ 8T = 216
⇒ T = 27 days
Ultra Calci trickLCM work
LCM 144: P = 4, Q = 3, R = 1 per day, total work 144; T = total days → R works T, Q works T − 8, P works T − 12
4(T − 12) + 3(T − 8) + T = 144 → 8T = 144 + 72 = 216
T = 216/8 = 27
⇒ 24 ✗ 30 ✗ 25 ✗
⇒ 27 ✓
P, Q और R अलग-अलग कार्य करते हुए किसी कार्य को क्रमशः 36 दिनों, 48 दिनों और 144 दिनों में पूरा कर सकते हैं। P, Q और R एक साथ कार्य करना शुरू करते हैं। P कार्य पूरा होने से 12 दिन पहले कार्य छोड़ देता है और Q कार्य पूरा होने से 8 दिन पहले कार्य छोड़ देता है। R शुरू से अंत तक कार्य करता है। कार्य पूरा करने में लगे कुल दिनों की संख्या ज्ञात कीजिए।
(SSC CPO Paper-1 2023 (03 Oct 2023, Shift 1))
- 24
- 27
- 30
- 25
उत्तर (विस्तृत हल नीचे)
विकल्प 2 : 27
विस्तृत हल
कॉन्सेप्ट से हल
LCM(36, 48, 144) = 144
⇒ P = 4, Q = 3, R = 1
कुल T दिन: R = T, Q = T − 8, P = T − 12
4(T − 12) + 3(T − 8) + T = 144
⇒ 8T = 216
⇒ T = 27 दिन
अल्ट्रा कैलसी ट्रिकLCM work
LCM 144: P = 4, Q = 3, R = 1 प्रतिदिन, कुल कार्य 144; कुल दिन T → R: T, Q: T − 8, P: T − 12 दिन
4(T − 12) + 3(T − 8) + T = 144 → 8T = 144 + 72 = 216
T = 216/8 = 27
⇒ 24 ✗ 30 ✗ 25 ✗
⇒ 27 ✓