15 men and 21 women together can complete a work in 56 days, while 12 men and 24 women together can complete it in 64 days. In how many days can 18 men and 24 women together complete the same work?

(SSC CGL Tier-1 2023)
  1. 47 6/19
  2. 47 9/19
  3. 47 5/19
  4. 47 3/19
Answer (Detailed Solution Below)
Option 4 : 47 3/19

Detailed Solution

Concept approach

(15m + 21w)56 = (12m + 24w)64

⇒ 72m = 360w

⇒ m = 5w. Work = 96w × 56 = 5376

⇒ 18m + 24w = 114w

⇒ 5376/114 = 47 3/19