Selection KeySelection KeyFree Mock Test
View this question in:

A can complete a piece of work in 25 days. After working for 5 days, the remaining work is completed in 15 days with the help of B. Then B can complete the whole work in how many days?

  1. 72 days
  2. 75 days
  3. 60 days
  4. 90 days
Answer (Detailed Solution Below)
Option 2 : 75 days

Detailed Solution

Concept approach

A in 5 days = 1/5

⇒ 4/5 by (A + B) in 15 days

⇒ A + B = 4/75

⇒ B = 4/75 − 3/75 = 1/75

⇒ 75 days