Selection KeySelection KeyFree Mock Test
View this question in:

4 persons, P, Q, R, S were engaged for doing a task, with the condition that P, Q, R, S work respectively on (Mondays, Thursdays), (Tuesdays, Fridays), (Wednesdays, Saturdays) and (Sundays). The work began on a Monday and got completed on the 15th day, which was also a Monday. If the efficiencies of P, Q, R, S in respect of doing this task were in the proportion 1 : 2 : 3 : 4, then in how many days could R complete the task, working alone without break?

(SSC MTS (12 Oct 2021))
  1. 13
  2. 10
  3. 11
  4. 12
Answer (Detailed Solution Below)
Option 3 : 11

Detailed Solution

Concept approach

One week = 1 + 2 + 3 + 1 + 2 + 3 + 4 = 16

⇒ 15 days = 2 weeks + Monday = 32 + 1 = 33

⇒ R alone = 33/3 = 11 days