A can do a work in 40 days. B is 66⅔% less efficient than A and C is 400% more efficient than B. All three started together. If B and C left the work 5 days and 2 days before its completion respectively, in how many days was the whole work completed?

(ICAR 2022)
  1. 16
  2. 18
  3. 15
  4. 20
Answer (Detailed Solution Below)
Option 3 : 15

Detailed Solution

Concept approach

A : B : C = 3 : 1 : 5, total = 120. 3T + (T − 5) + 5(T − 2) = 120

⇒ 9T = 135

⇒ T = 15 days