40 men can complete a work in 15 days. Three days after they started working, 20 more men joined them. In how many days the total work will be completed?

(SSC CGL Tier-1 2022 (5 Dec · Shift 3 · 2:30 PM))
  1. 12
  2. 13
  3. 11
  4. 10
Answer (Detailed Solution Below)
Option 3 : 11

Detailed Solution

Concept approach

Work = 40 × 15 = 600; in 3 days 120 done

⇒ 480 left by 60 men = 8 days

Total = 3 + 8 = 11 days