Sonia can do 1/3rd of a work in 5 days, Tuktuk can do 2/5th of the same work in 10 days and Pamela can do 3/4th of the work in 15 days. They all start working together. After 3 days, Sonia leaves. Tuktuk and Pamela work together for another 2 days before Tuktuk leaves. Pamela then finishes the remaining work alone. For how many total days did Pamela work on the project?

(SSC CGL 2026 (5 Oct, Shift 1))
  1. 9
  2. 10
  3. 11
  4. 12
Answer (Detailed Solution Below)
Option 4 : 12

Detailed Solution

Concept approach

Full work: Sonia 15 d, Tuktuk 25 d, Pamela 20 d. LCM 300: 20, 12, 15 per day

All 3 days: 47 × 3 = 141; T+P 2 days: 27 × 2 = 54

⇒ 195

Left 105 ÷ 15 = 7 days

Pamela = 3 + 2 + 7 = 12 days

Ultra Calci trickLCM work

Full work: S 15, T 25, P 20 days

⇒ LCM 300

⇒ efficiency 20, 12, 15

Day 1–3: 3 × 47 = 141; next 2 days (T + P): 2 × 27 = 54

⇒ done 195, left 105

P alone: 105/15 = 7 days

⇒ total P = 3 + 2 + 7 = 12

⇒ 12 days ✓