A contractor employed 69 workers to complete a work in 20 days. How many more workers he should employ to complete the work in 12 days?
(SSC CHSL 2023 (03 Aug 2023, Shift 2))
- 115 workers
- 46 workers
- 51 workers
- 64 workers
Answer (Detailed Solution Below)
Option 2 : 46 workers
Detailed Solution
Concept approach
Work = 69 × 20 = 1,380 man-days
Workers for 12 days = 1,380/12 = 115
⇒ extra = 115 − 69 = 46.