Selection KeySelection KeyFree Mock Test

A contractor employed 69 workers to complete a work in 20 days. How many more workers he should employ to complete the work in 12 days?

(SSC CHSL 2023 (03 Aug 2023, Shift 2))
  1. 115 workers
  2. 46 workers
  3. 51 workers
  4. 64 workers
Answer (Detailed Solution Below)
Option 2 : 46 workers

Detailed Solution

Concept approach

Work = 69 × 20 = 1,380 man-days

Workers for 12 days = 1,380/12 = 115

⇒ extra = 115 − 69 = 46.