A and B are in the ratio 7:5 in efficiency. A alone can complete the work in 55 days. How long will B take to finish it alone?

(SSC Selection Post 2026 (Higher Secondary, 21 Sep, Shift 2))
  1. 77 days
  2. 67 days
  3. 57 days
  4. 54 days
Answer (Detailed Solution Below)
Option 1 : 77 days

Detailed Solution

Concept approach

Efficiency 7:5

⇒ time 5:7; B = 55 × 7/5 = 77 days

Ultra Calci trickmultiple-of-7

Efficiency 7 : 5 → days 5 : 7 → B = 55 × 7/5 → multiple of 7 (55 ÷ 5 = 11 → 11 × 7)

67 ✗ 57 ✗ 54 ✗ 77 ✓

⇒ 77 days