Lalit can finish a work in 15 days. Laxman can finish the same work in 25 days. They work together for 5 days. If the rest of the work is finished by Lalit and Deven in 4 days, then in how many days can Deven alone finish the work?

(SSC CGL Tier-1 2025 (26 Sep · Shift 3 · 4:00 PM))
  1. 30 days
  2. 25 days
  3. 21 days
  4. 20 days
Answer (Detailed Solution Below)
Option 4 : 20 days

Detailed Solution

Concept approach

LCM 75: Lalit = 5, Laxman = 3 per day

⇒ 5 days × 8 = 40

Remaining 35 in 4 days = 8.75/day

⇒ Deven = 8.75 − 5 = 3.75

⇒ 75/3.75 = 20 days

Ultra Calci trickLCM work

LCM 75 → Lalit 5, Laxman 3 → 5 days = 40 → left 35

Lalit + Deven in 4 days: 20 + 4D = 35 → D = 3.75 → 75/3.75 = 20 days

⇒ 20 days