A can complete 1/3 of a work in 7 days and B can complete 2/7 of the same work in 10 days. In how many days can both A and B together complete the work?

(SSC CGL Tier-1 2023 (25 Jul · Shift 2 · 11:45 AM))
  1. 12⅜
  2. 11⅞
  3. 13⅛
  4. 15⅐
Answer (Detailed Solution Below)
Option 3 : 13⅛

Detailed Solution

Concept approach

A: 1/3 in 7 days

⇒ 21 days; B: 2/7 in 10 days

⇒ 35 days

⇒ LCM 105: eff 5 + 3 = 8

⇒ 105/8 = 13 1/8 days

Ultra Calci trickLCM work

A: 21 days, B: 35 days → LCM 105 → A 5, B 3 → 8 per day

105/8 = 13⅛

⇒ 13⅛