A can do a piece of work in 10 days, while A and B together can complete it in 2½ days. How long will B alone take to complete the work?

(SSC CPO Paper-1 2022 (09 Nov 2022, Shift 2))
  1. 3/10 days
  2. 10/3 days
  3. 3 days
  4. 4 days
Answer (Detailed Solution Below)
Option 2 : 10/3 days

Detailed Solution

Concept approach

Total work = 10 (LCM style): A = 10/10 = 1/day

A + B = 10/2.5 = 4/day

⇒ B = 3/day

Time = 10/3 days