A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B works only half a day daily, then in how many days will A and B together complete the work?

  1. 14 days
  2. 10 days
  3. 15 days
  4. 20 days
Answer (Detailed Solution Below)
Option 3 : 15 days

Detailed Solution

Concept approach

Total = 60; A+B = 5, A = 3

⇒ B = 2; half day

⇒ 1. Together 3 + 1 = 4

⇒ 60/4 = 15 days