A and B can finish a work in 10 days, B and C can finish it in 12 days and C and A can finish in 6 days. In how many days A alone can finish the work?

(SSC CGL Tier-1 2023 (18 Jul · Shift 3 · 2:30 PM))
(SSC CGL 18.07.2023)
  1. 120/9
  2. 12
  3. 120/11
  4. 121/12
Answer (Detailed Solution Below)
Option 3 : 120/11

Detailed Solution

Concept approach

2(A + B + C) = 1/10 + 1/12 + 1/6 = 21/60

⇒ A + B + C = 21/120

A = 21/120 − 1/12 (B + C) = 11/120

⇒ 120/11 days

⇒ C