12 men can complete a work in 10 days. How many more men are required to complete the work in 6 days?

(SSC CGL Tier-1 2023 (19 Jul · Shift 4 · 5:15 PM))
(SSC CGL Pre 2023)
  1. 24
  2. 10
  3. 8
  4. 20
Answer (Detailed Solution Below)
Option 3 : 8

Detailed Solution

Concept approach

Work = 12 × 10 = 120

⇒ in 6 days 120 ÷ 6 = 20 men

⇒ more = 20 − 12 = 8