A and B can together complete a piece of work in 18 days, B and C can together complete the same work in 24 days and A and C can together complete it in 36 days. In how many days can A, B and C, working together, complete this piece of work?

(SSC MTS 2022 (05 Jul 2022, Shift 3))
  1. 19
  2. 16
  3. 20
  4. 14
Answer (Detailed Solution Below)
Option 2 : 16

Detailed Solution

Concept approach

Efficiency (LCM 72): A + B = 4, B + C = 3, A + C = 2

⇒ 2(A + B + C) = 9

⇒ A + B + C = 4.5

⇒ 72/4.5 = 16 days.

Ultra Calci trickLCM work

LCM 72 → A + B = 4, B + C = 3, A + C = 2 → 2 × all = 9 → 4.5 per day

72/4.5 = 16 days

⇒ 16