A can finish one-third of a work in 5 days, B can finish 2/5 of the same work in 10 days and C can finish 75% of the work in 15 days. They work together for 6 days. The remaining work will be finished by B alone in:

  1. 5 days
  2. 3 days
  3. 2 days
  4. 1½ days
Answer (Detailed Solution Below)
Option 4 : 1½ days

Detailed Solution

Concept approach

6 days: A 40%, B 24%, C 30% = 94%

⇒ 6% left; B does 4% a day

⇒ 6/4 = 1½ days

Ultra Calci trickLCM work / efficiency

A: 1/3 in 5 days

⇒ 15 days; B: 2/5 in 10

⇒ 25 days; C: 75% in 15

⇒ 20 days

LCM 300

⇒ A 20, B 12, C 15 per day

⇒ 47 × 6 = 282 done, 18 left

B alone: 18/12 = 1½ days