Selection KeySelection KeyFree Mock Test
View this question in:

A, B and C can do a piece of work in 32, 48 and 24 days respectively. They work together for 4 days, then A leaves. B and C work for 2 more days, then B leaves and the remaining work is done by C. If they get ₹6840 for the whole work, find the share of C.

  1. ₹5860
  2. ₹3240
  3. ₹5130
  4. ₹4840
Answer (Detailed Solution Below)
Option 3 : ₹5130

Detailed Solution

Concept approach

A's work = 4/32 = 1/8, B's work = 6/48 = 1/8

⇒ C did 3/4

⇒ 6840 × 3/4 = ₹5130

Ultra Calci trickLCM work + T1

LCM 96 → A 3, B 2, C 4 per day. 4 days all: 36; 2 days B + C: 12

⇒ left 48 for C

C's work = 16 + 8 + 48 = 72 of 96 = 3/4

Share = 6840 × 3/4 = 5130

⇒ 5860 ✗ 3240 ✗ 4840 ✗

⇒ ₹5130 ✓