Abha and Anuj together completed a work in 40/9 days. If Abha had worked with twice her actual efficiency and Anuj with 1/3 of his actual efficiency, the work would have been completed in 60/17 days. How much time would Abha alone take to complete the work?

(SSC CGL Tier-1 2022)
  1. 10 days
  2. 6 days
  3. 12 days
  4. 8 days
Answer (Detailed Solution Below)
Option 4 : 8 days

Detailed Solution

Concept approach

(A + N) × 40/9 = (2A + N/3) × 60/17

⇒ 680A + 680N = 1080A + 180N

⇒ A : N = 5 : 4

⇒ work = 9 × 40/9 = 40

⇒ Abha 40/5 = 8 days