A contractor decided to complete a work in 80 days and employed 60 men at the beginning and 20 men additionally after 20 days and got the work completed as per schedule. If he had not employed the additional men, how many extra days would he have needed to complete the work (round off to the nearest integer)?

(SSC CGL Tier-1 2022 (5 Dec · Shift 2 · 11:45 AM))
  1. 32 days
  2. 20 days
  3. 30 days
  4. 26 days
Answer (Detailed Solution Below)
Option 2 : 20 days

Detailed Solution

Concept approach

Work = 60 × 20 + 80 × 60 = 1200 + 4800 = 6000 man-days

With 60 men only = 100 days

⇒ 100 − 80 = 20 extra days