10 men can do a work in 25 days. After 12 days of work, 3 more men were engaged to finish the work. The number of days required to complete the remaining work is:

(SSC CGL Tier-1 2023 (18 Jul · Shift 1 · 9:00 AM))
(SSC CGL Pre 2023)
  1. 10
  2. 8
  3. 6
  4. 12
Answer (Detailed Solution Below)
Option 1 : 10

Detailed Solution

Concept approach

Work = 10 × 25 = 250

⇒ done 10 × 12 = 120

⇒ left 130

⇒ 130/13 men = 10 days

⇒ A