A company deploys 500 labourers to restore an old fort wall. In the first 15 weeks, they manage to rebuild 2/5 of the total structure. Suddenly, a severe storm hits the region, causing the restoration work to be stopped for 6 weeks. During this period of inactivity, 1/2 of the portion already restored collapses due to the storm damage. When the weather clears and the restoration resumes, only 360 labourers return to work. Assuming that no further interruptions occur, in how many weeks from the beginning will the entire restoration project be completed?
(SSC Selection Post 2026 (Higher Secondary, 26 Sep, Shift 1))
- 42.33 weeks
- 57.23 weeks
- 62.67 weeks
- 55.25 weeks
Answer (Detailed Solution Below)
Option 3 : 62.67 weeks
Detailed Solution
Concept approach
Work per labourer-week = (2/5)/(500 × 15) = 1/18750; left = 4/5 (1/5 restored); time = (4/5) × 18750/360 = 41.67 weeks; total = 15 + 6 + 41.67 = 62.67
एक कंपनी एक पुरानी किले की दीवार की मरम्मत के लिए 500 मज़दूर लगाती है। पहले 15 सप्ताह में, वे कुल संरचना के 2/5 भाग का पुनर्निर्माण कर लेते हैं। अचानक, क्षेत्र में एक भीषण तूफ़ान आता है, जिससे मरम्मत कार्य 6 सप्ताह के लिए रुक जाता है। इस निष्क्रियता की अवधि के दौरान, तूफ़ान से हुई क्षति के कारण पहले से पुनर्निर्मित भाग का 1/2 भाग ढह जाता है। जब मौसम साफ़ होता है और मरम्मत फिर शुरू होती है, तो केवल 360 मज़दूर काम पर लौटते हैं। यह मानते हुए कि कोई और रुकावट नहीं आती, शुरुआत से कितने सप्ताह में संपूर्ण मरम्मत परियोजना पूरी होगी?
(SSC Selection Post 2026 (Higher Secondary, 26 Sep, Shift 1))
- 42.33 सप्ताह
- 57.23 सप्ताह
- 62.67 सप्ताह
- 55.25 सप्ताह
उत्तर (विस्तृत हल नीचे)
विकल्प 3 : 62.67 सप्ताह
विस्तृत हल
कॉन्सेप्ट से हल
प्रति मज़दूर-सप्ताह कार्य = (2/5)/(500 × 15) = 1/18750; शेष = 4/5 (1/5 बचा); समय = (4/5) × 18750/360 = 41.67 सप्ताह; कुल = 15 + 6 + 41.67 = 62.67